The last two weeks we have installed the steel structure and the hollow core concrete planks. It took us about one week to install and detail all of the steel. We used the large Crane on site to set steel. A few days later we received 15 truckloads of concrete planks. These planks are used to spanned the distance from the North side of the building to the South side and make up your floor system. I have attached several pictures showing the progress. We are presently installing the underground plumbing in the lower level of the facility. We will continue to back fill the basement walls up to grade starting this Friday the 18th. Within the next couple of weeks we will start to frame the exterior walls of the building.